Deprecated: Assigning the return value of new by reference is deprecated in /data/16/1/144/102/1470265/user/1580605/htdocs/constructionblog/wp-settings.php on line 512

Deprecated: Assigning the return value of new by reference is deprecated in /data/16/1/144/102/1470265/user/1580605/htdocs/constructionblog/wp-settings.php on line 527

Deprecated: Assigning the return value of new by reference is deprecated in /data/16/1/144/102/1470265/user/1580605/htdocs/constructionblog/wp-settings.php on line 534

Deprecated: Assigning the return value of new by reference is deprecated in /data/16/1/144/102/1470265/user/1580605/htdocs/constructionblog/wp-settings.php on line 570

Deprecated: Assigning the return value of new by reference is deprecated in /data/16/1/144/102/1470265/user/1580605/htdocs/constructionblog/wp-includes/cache.php on line 103

Deprecated: Assigning the return value of new by reference is deprecated in /data/16/1/144/102/1470265/user/1580605/htdocs/constructionblog/wp-includes/query.php on line 61

Deprecated: Assigning the return value of new by reference is deprecated in /data/16/1/144/102/1470265/user/1580605/htdocs/constructionblog/wp-includes/theme.php on line 1109
June « 2008 «

Archive for June, 2008

June 26: Stuck in Traffic, Change of Plans

Thursday, June 26th, 2008

St. Mark's Lutheran School classroom addition

Bridges out. Roads closed. Detours. These are the road conditions we’ve all been tolerating the past two weeks as we recover from what the media now calls the “Flood of 2008.”

For the most part, the weather and resulting inconveniences haven’t affected our project. This week, however, they did. The plan was to have semi trucks deliver large, precast, cement floor panels for the new classrooms. Because of flood-related road closings, however, the trucks were unable to get through. Yes, this causes a bit of a delay. But while they wait, crews redirect their work to the west end of the building.

Other plans change as well
As you walk through the site, you see sets of floor plans everywhere. Why so many? Are they all the same?

“Each contractor working on site has a set of plans,” Maas Brothers construction superintendent Matt Hollman explains, “The electricians, the plumbers, the heating guys—they all have a set of plans and they’re all the same. They each have to know what the other is doing.”

Floor plans are ever-changing according to construction needs. Each time they’re revised, each contractor receives an updated version with the changes clearly marked.

“For I know the plans I have for you,” declares the Lord, “plans to prosper you and not to harm you, plans to give you hope and a future,” Jeremiah 29:11.

 

June 19: Walls Come Down, Walls Go Up

Thursday, June 19th, 2008

What a difference a week makes! While Beaver Wrecking and Salvage, of Beaver Dam, demolishes the last of the necessary interior walls, Walsh Masonry, of Ixonia, lays exterior walls for the new classrooms. They’ve also begun footings for the offices located in the front, central area of the school.

There’s a lot happening inside the building as well. Midwest Electric, of Watertown, has been installing outlets in the existing classrooms and Monona Plumbing, of Madison, is laying pipes for the ground floor bathrooms. Here, the teacher’s lounge is now plumbed to be the girls bathroom.

In what used to be the cafeteria, crews have installed shoring to support the ceiling when a portion of the wall is removed for the incoming elevator.

An interesting bit of St. Mark’s history
This week we had Hepp Excavating in to remove a foundation from the old 1915 school. Along with the foundation were footings for a breezeway that connected the old school to the new school (new, that is, if you’re in your 40’s and 50’s). How many of you remember walking that breezeway from one school to the other?

And how’s the weather been?
While much of Watertown is still drying out, St. Mark’s continues to appreciate its sandy soil, which project superintendent Matt Hollman says “drains very well.” The only negative effect from the weather has been unloading the demolition debris.

“We had trouble getting rid of the demolition material because the ground at our dumping site is too soft,” says Matt. “We can’t get in with the trucks. So now, we’re taking it to another pit.”

Overall, the project is going very well. From 6 a.m. to 5 p.m., anyone in the neighborhood will hear and see lots of activity. God’s blessings on the activity!

June 12: A wet, wet week

Thursday, June 12th, 2008

St. Mark's Lutheran School kitchen demolition

The week started with more than seven inches of rain, causing flooding for many Watertown areas. As the week progresses, we continue to get downpours. Yet God guides our project. “We’ve been very lucky in spite of the rain,” says Matt Hollman, Maas Brothers superintendent for the project. “Because we’ve got sandy soil, the water’s not sitting around. We had four inches of water in the footings but we were able to pump it out with no problem.” Interstate Sawing demolition robot Demolition continues this week, including tearing out the stairs—a rather interesting job done by a robot. The robot, from Interstate Sawing Co., of West Bend, provides a safety measure that keeps everyone away from falling debris. Here, the robot knocks out the stairs along side the library and cafeteria. And yes, that’s the cafeteria in the top photo, minus its interior walls. No more jog in the hallway… Looks like there’s been a lot of tearing and knocking things down. But there’s been more. Crews began pouring footings for the new classrooms, located toward the east end of the building. This means construction has officially begun! Please keep the work crews in your prayers. Pray for their safety as they finish demolition this week.

June 5: And so we begin

Thursday, June 5th, 2008

School demolition begins

What kid wouldn’t enjoy this scene—the knocking down of a school! This was a big week of demolition. Down came the gymnasium and many inner walls, all necessary to make room for a new gymnasium, classrooms and kitchen.

Check out the photo gallery for more!

June 1: Groundbreaking

Monday, June 2nd, 2008

Wonderful weather, glowing T-shirts and great excitement!

God blessed St. Mark’s with all of the above as we broke ground for our school addition and renovation. Held on Sunday, June 1, in conjunction with the annual church picnic, this officially marks the start of our project.

St. Mark's Lutheran Church Groundbreaking

Breaking ground are (l-r) Tom Hahn of Town and Country Bank; Dan Shea of Maas Brothers Construction; Charles Higgins; Tim Fredrick, St. Mark’s building committee chairman; eighth grade student K. Wollitz; kindergarten student S. Gray; Roy Zastrow; Harold Peckham; Vernon Zastrow (seated); Fred Uttech, St. Mark’s School principal; A.J. Ritschke; and Matt Nottling.

St. Mark’s has enjoyed its annual church picnic since the 1890’s and generations of children have marched in our parades. Yet, not many have lined up in front of construction equipment —certainly a memorable parade!

Certainly a blessed and memorable day!